The project includes excavation, grading, steel sheetpile installation, tile and CMP conduit installation, riprap with concrete grout, TURF reinforcement mat Type 5B, silt fence, and seeding. Construction is scheduled to begin on November 1, 2027, with seeding to be completed by December 15, 2027, following the seeding windows in IA CS-006. Seeding must be completed during approved periods: Spring (March 1–May 15), Summer (August 1–September 15), or Fall (November 15–Freeze-up). The contractor is responsible for all mobilization and demobilization activities, including access grading and temporary culverts. Portable toilets must be provided on-site. Concrete grout must be placed within 1.5 hours of mixing and must not be dropped more than 5 feet vertically. The contractor must ensure that all materials are free of debris, and all rock must be screened to remove material less than 8 inches in size.
On PublicBidSearch: the original bid posting, 6 bid documents and the agency contact (name, email and phone) for this bid.
Contact
Agency contact for this bidName, email and phone — included with ProProOverview
- Due
- Dec 10, 2026, 11:59 PM CT
- Time stated in bid documents
- Dec 10, 2026, 11:59 PM Central Time
- Submission
- electronic portal
- Contract term
- 3 years + Two additional one-year renewal terms
- Documents analyzed
- 6 published · 1 analyzed
Scope of work
- Construct 18,151 cubic yards of earthwork
- Install 1,150 square feet of steel sheetpile
- Install 1,268 linear feet of pipe
- Place 668 tons of riprap
- Install 35 tons of 2” clean stone
- Place 72 cubic yards of concrete grout
Steps to Bid
- 1
Register with the Iowa Bid Opportunities portal
Visit [link available with Pro] and create an account to access the full bid package.
What you'll need
Submission
Electronic portal
NAICS
237190, 237990
Pursuit snapshot
Pro- Go / no-go verdict on every requirement
- 7 watch-outs that disqualify bidders
Cancel anytime · no card to browse
Project details
All work must comply with OSHA safety requirements and NRCS standards. If construction is completed outside these periods, seeding must occur at the next available window. No mulch is required for buffer seeding. Weed control may be added via change order and paid for by the contractor if needed. Grout must be consolidated using a vibrator and must not be placed in standing or flowing water.
Key dates
- Questions due
- Dec 1, 2026, 11:59 PM Central Time
- Bids due
- Dec 10, 2026, 11:59 PM CT
Documents
- Plan_Set.pdf
- Standards_and_Specifications.pdf57 pages
- Schedule_of_Prices_.pdf1 pages
- Shive-Hattery_Inspection_Report.pdf4 pages
- Bid_Bond.pdf1 pages
- Proposal-Acknowledgement-Affidavit.pdf3 pages
More from this agency
- Conventional Nutrient Reduction Wetland Construction — closes Dec 10, 2026
- 26-14 Sto822305D (Story) — closes Dec 10, 2026
Similar open bids
- Professional Design Services for Window Replacement at North Central Correctional Facility R&D Building — Administrative Services, Dept
- Peninsula Apartments Exterior Repairs Project — City of Iowa City
- Window Treatments and Associated Services — Administrative Services, Dept
Closing this week nearby
- Kanawha Public Library: E-Rate FY2027 Internet Access and Data Transmission Service — closes Nov 20, 2026
- Everly Public Library: E-Rate FY2027 Category 1 - Internet Access and Data Transmission Service — closes Nov 22, 2026
- ICN OSP Project #77244807, Polk County – Cable Relocation and Conduit Installation — closes Nov 23, 2026
- ICN OSP Project #77244807, Polk County – City of Des Moines Cable Relocation — closes Nov 23, 2026
- Light Duty Trucks, MY27 Chevrolet Silverado & GMC Sierra 1500 or Equivalent — closes Nov 23, 2026