Holly Street Bridge Seismic Retrofit and Rehabilitation Project (HBP) [CIP No. 73323]
City of Pasadena — Public Works Department, EngineeringPasadena, California#2026-IFB-CIV-0063
The City of Pasadena, in coordination with Caltrans, is soliciting bids for the seismic retrofit and comprehensive rehabilitation of the Holly Street Bridge (No. 53C1041) over the Arroyo Seco Channel, the Arroyo Seco Trail, and North Arroyo Boulevard. Scope includes deck treatment, repair of spalled concrete, rehabilitation of bridge girders with exposed rebar, and ADA-compliant upgrades to adjacent sidewalks, curbs, and curb ramps at Linda Vista Avenue and Holly Street. The project is federally funded via the FHWA Highway Bridge Program (HBP), and all contractors must comply with federal, state, and local requirements for federally funded work.
On PublicBidSearch: the original bid posting for this bid.
Overview
- Due
- Dec 8, 2026
- Time stated in bid documents
- Dec 8, 2026, 2:00 PM Pacific Time
- Submission
- mail, hand delivery
Steps to Bid
- 1
Review the solicitation and all attached documents (if available) to understand scope, requirements, and submission instructions.
- 2
Register with the City of Pasadena procurement portal (if required) and obtain access to the bid package.
- 3
Submit a complete bid package by the due date and time. by Dec 8, 2026, 2:00 PM
What you'll need
Submission
Mail, Hand delivery
NAICS
237130, 237199
Pursuit snapshot
Pro- Go / no-go verdict on every requirement
- 2 watch-outs that disqualify bidders
Cancel anytime · no card to browse
Project details
The City of Pasadena, in coordination with the California Department of Transportation (Caltrans), proposes to rehabilitate and seismically retrofit the existing two-lane Holly Street Bridge (No. 53C1041) over the Arroyo Seco Channel, the Arroyo Seco Trail (a Class 1 multi-use trail), and North Arroyo Boulevard. The project includes seismic retrofit and comprehensive bridge rehabilitation work such as deck treatment, repair of spalled concrete, and rehabilitation of bridge girders with exposed reinforcing steel to address structural deficiencies and extend the service life of the facility. It also includes upgrades to adjacent pedestrian facilities—sidewalk, curb and gutter, and new curb ramps—at the intersection of Linda Vista Avenue and Holly Street to bring them into compliance with current Americans with Disabilities Act (ADA) standards. The project is funded by the Federal Highway Administration (FHWA) through the Highway Bridge Program (HBP), authorized by U.S. Code Title 23 and administered by Caltrans. The Contractor must comply with all applicable federal, state, and local laws, regulations, and requirements associated with federally funded projects.
Key dates
- Bids due
- Dec 8, 2026
More from this agency
- On-Call Parking Consultant Services · closes Dec 9, 2026
- Installation of Ductile Iron Water Mains in Catalina Ave - WD-27-01 · closes Dec 10, 2026
- Rental Registry Database and Online Portal for City of Pasadena · closes Dec 10, 2026
- Heavy-Duty Radiator Repair, Service, and OEM Parts · closes Dec 10, 2026
- Fire Extinguisher Inspection, Maintenance, Testing, Repair, Recharging, Hydrostatic Testing, Replacement, and Parts… · closes Dec 10, 2026
Similar bids near Pasadena
- La Verne Pedestrian Bridge · Alhambra · closes Dec 17, 2026
- BRIDGE REPAIR MAINTENANCE GROUP 2 (RE-BID) · Los Angeles · closes Dec 9, 2026
- Championship Bridge Civil Improvements, CIP 700004 · Irvine · closes Dec 3, 2026
Closing soon near Pasadena
- Wood Pole Inspection, Treatment, Repair, and UAV Inspection Services · Pasadena · closes Dec 2, 2026
- Purchase of Off-Highway Vehicles (OHV) for Pasadena Police Department · Pasadena · closes Dec 3, 2026
- Caltrans Real Properties: Security Services · Pasadena · closes Dec 4, 2026
- Public Records Act System Replacement – Request for Information · Pasadena · closes Dec 4, 2026
- Virtual Mailroom Services · Pasadena · closes Dec 5, 2026