Construction of Water Main Relocation for State Route 20 Widening Project

Cherokee County Water And Sewerage AuthorityGeorgia#PE-33957-NONST-2027-000000022

The Cherokee County Water and Sewerage Authority is seeking sealed bids for the construction of a water main relocation project along State Route 20, including 11,360 LF of 36-inch DIP, 1,400 LF of 20-inch DIP, 15,500 LF of 12-inch DIP, and 20,200 LF of 8-inch DIP water mains. Work must be completed within 960 days for substantial completion and 1,640 days for final completion. Bids must be submitted on the official form and received by December 17, 2026, at 10:00 AM local time. Questions must be submitted by December 9, 2026, at 3:00 PM. Plans and specifications are available at the Authority’s office in Canton, Georgia, and at AtkinsRealis USA in Marietta, Georgia.

On PublicBidSearch: the original bid posting, 1 bid document and the agency contact (name, email and phone) for this bid.

Open Original Bid Source Pro

Contact

Agency contact for this bidName, email and phone — included with ProPro

Overview

Due
Dec 17, 2026
Time stated in bid documents
Dec 17, 2026, 10:00 AM Eastern Time
Submission
mail, hand delivery
Documents analyzed
1
Required submission items
1 items · full checklist with Pro

Scope of work

  • Coordinate with GDOT road contractor for alignment and timing
  • Abandon and remove all existing water mains

Steps to Bid

  1. 1

    Register with the Engineer of Record (AtkinsRealis USA) to receive plans and specifications.

  2. 2

    Review the full bid documents, including plans, specifications, and contract terms.

  3. 3

    Submit the completed bid form, signed and sealed, to the Cherokee County Water and Sewerage Authority at 110 Railroad Street, Canton, Georgia, 30114. by Dec 17, 2026, 10:00 AM

  4. 4

    Ensure the bid is received by the deadline and is not altered after submission. by Dec 17, 2026, 10:00 AM

What you'll need

Contract duration

960 calendar days for substantial completion, 1,640 consecutive calendar days for final completion

Award method

The Owner reserves the right to reject any or all Bids, to waive formalities, re-advertise, and to reduce or add to the contract from time to time.

Submission

Mail, Hand delivery

NAICS

237130, 237199

Pursuit snapshot

Pro
  • Go / no-go verdict on every requirement
  • 1 watch-out that disqualifies bidders
  • The 1-item required-submittals checklist
Unlock with Pro — $20/mo

Cancel anytime · no card to browse

Project details

Work must be coordinated with the Georgia Department of Transportation (GDOT) road contractor. Maximum time for substantial completion is 960 calendar days, including material procurement, full installation of all proposed water mains and services, abandonment of existing mains, and initial record drawing survey. Maximum time for final completion is 1,640 consecutive calendar days, including punch list and close-out work. All bids must be submitted on the official bid form and may not be altered.

Key dates

Questions due
Dec 9, 2026, 3:00 PM Eastern Time
Bids due
Dec 17, 2026

Documents

  • 202611_supportingdocs_PE-33957-NONST-2027-000000022-2026-11-19_13_45_45-352c.pdf2 pages