Green St. Corridor Improvements – Phase 1
Town of BrownsburgBrownsburg, Indiana#25-0091
The Town of Brownsburg, Indiana, is soliciting sealed bids for the Green St. Corridor Improvements – Phase 1 project, which includes installation of a new traffic signal at Green St. and Whittington Drive, minor traffic signal upgrades at Green St. and the I-74 westbound ramp, and median installation to restrict turning movements at Green St. and the Kroger entrance. Bids are due by 11:00 a.m. local time on December 10, 2026, at the Town Hall Reception Area. All bids will be publicly opened and read immediately after the deadline.
On PublicBidSearch: the newspaper notice for this bid.
Overview
- Due
- Dec 10, 2026
- Time stated in bid documents
- Dec 10, 2026, 11:00 AM Eastern Time
- Submission
- mail, hand delivery
Scope of work
- Complete work within 120 days of Notice to Proceed
- Comply with all local, state, and federal traffic safety standards
Steps to Bid
- 1
1
Review the full solicitation and contract documents, available electronically upon request via email.
- 2
2
Submit a sealed bid in person to the Town of Brownsburg Town Hall Reception Area at 61 N Green St, Brownsburg, IN 46112, by 11:00 a.m. local time on Thursday, December 10, 2026.
- 3
3
Bids will be opened and publicly read aloud immediately after 11:00 a.m. in the council room.
What you'll need
Submission
Mail, Hand delivery
How to submit
Bids must be submitted in sealed envelopes and delivered in person to the Town of Brownsburg Town Hall Reception Area. No electronic submissions are accepted.
In person/mail: 61 N Green St, Brownsburg, IN 46112
Pursuit snapshot
Pro- Go / no-go verdict on every requirement
- 2 watch-outs that disqualify bidders
Cancel anytime · no card to browse
Project details
All bids will be opened and publicly read aloud immediately after 11:00 a.m. in the council room. Contract documents are on file electronically and may be ordered via email.
Key dates
- Bids due
- Dec 10, 2026
More from this agency
- Wastewater Projects 2026-27: Main Plant Improvements (Project #S26124) — closes Dec 3, 2026
- Wastewater Projects 2026-27: Main Plant Improvements and Nelson Lift Station Upgrades — closes Dec 3, 2026
- Low Pressure Sewer System - Unsewered Neighborhood Improvements — closes Dec 8, 2026
- Low Pressure Sewer System Construction for Unsewered Neighborhoods in Brownsburg, Indiana — closes Dec 8, 2026
- Advertisement for Bids: Green St. Corridor Improvements — closes Dec 10, 2026
Similar open bids
- Intersection Improvement, Roundabout - US 231 at Iowa Street (Lake County) — Indiana DOT
- Grimes Lane at Walnut Street Signal Replacement — City of Bloomington IN
- 3rd Street Traffic Signal Improvements at S. Woodlawn Avenue and S. Hawthorne Drive — City of Bloomington IN
- 3rd Street Traffic Signal Improvements at S. Woodlawn Avenue & S. Hawthorne Drive — City of Bloomington
- Grimes Lane at Walnut Street Signal Replacement and Intersection Improvements — City of Bloomington
Closing this week nearby
- City Hall Building - Engineering Area Remodel — closes Nov 18, 2026
- Tree Trimming and Tree Mowing Control Services for 2027 — closes Nov 18, 2026
- Garrett-Keyser-Butler Middle School Roof Replacement — closes Nov 18, 2026