OpenRFPCloses Jan 5, 2027

Grawemeyer Switchgear Replacement & New Building

University of LouisvilleLouisville, Kentucky#1209010

This project involves constructing a new, climate-controlled switchgear building and installing an electrical duct bank with associated conduit. All excavation and underground utility work must occur during the summer break (May 15th - first week of August), with building construction continuing until November. Traffic flow and parking access must be maintained throughout the project. The bid requires a project schedule, and temporary power must be provided by the contractor during shutdowns. The bid due date is January 5, 2027, at 2:00 PM EST. A mandatory pre-bid meeting with a site walk is scheduled for December 1, 2026, at 1:00 PM EST at the Miller Information Technology Center (MITC). Written questions are due by December 7, 2026, at 2:00 PM EST. A bid bond of 5% of the bid amount is required. Performance and Payment Bonds are also required.

On PublicBidSearch: the original bid posting, 16 bid documents and the agency contact (email) for this bid.

Open Original Bid Source Pro

Contact

Agency contact for this bidEmail — included with ProPro

Overview

Due
Jan 5, 2027
Bid bond
5%
Performance bond
100%
Payment bond
100%
Submission
electronic portal
Documents analyzed
16 published · 12 analyzed

Scope of work

  • Rework of LG&E Algonquin Service, including restoration of asphalt, brick pavers, curbing, sidewalks, landscaping, and lawn areas.
  • Installation of Silt Fence as per MSD requirements.
  • All trenching, excavation, underground utilities, and conduits installation must be accomplished during the summer break (May 15th – 1st week of August).
  • Traffic flow over the Oval driveway and parking lot drive lanes must be maintained; open trenches must be metal-plated.

Steps to Bid

  1. 1

    Review Bid Documents, Instructions to Bidders, and Terms and Conditions.

  2. 2

    Submit Written Questions. by Dec 7, 2026, 2:00 PM

    Questions must be submitted via the University bidding platform Workday.

  3. 3

    Review Addendum for Questions (if issued). by Dec 14, 2026, 2:00 PM

What you'll need

Bid security

Required

Performance and Payment Bonds are required per 200KAR 5:305 Section 1. Failure to provide will result in loss of award of contract. 100% P&P Bonds are required when signing a contract.

Contract duration

Substantial Completion Date: 11/23/2027, Final Completion Date: 11/30/2027

Submission

Electronic portal

Pursuit snapshot

Pro
  • Go / no-go verdict on every requirement
  • 10 watch-outs that disqualify bidders
Unlock with Pro — $20/mo

Cancel anytime · no card to browse

Project details

Construction of a new switchgear building to house new medium voltage switchgear serving as a major junction in the underground distribution network on campus and Grawemeyer Hall. A cubic yard rate for over-excavation and backfill of unsuitable soils and materials at the location of the new building is required. A KYTC encroachment permit will be required for any utility work in the 3rd street state highway right-of-way. A MSD plan submission and permits are required. Pre-ordered equipment (Exhibit I) is provided for reference only for installation of Electrical gear’s concrete pads and underground feeders to electrical equipment. This equipment is stored in the owner's warehouse less than 2 miles from Belknap campus; the awarded contractor shall inspect and ship equipment to site. Equipment includes: 15KV, MV Switchgear- Indoor (Qty.1), 15KV, MV Metering Switchgear- Outdoor (Qty.1), 500KVA, 13.8kv- 208Y/120V LV Transformer – Indoor (Qty.1), MDP,1600A, 208Y/120V,3Ph, Grawemeyer Switchboard – Indoor (Qty.1). Contractor shall provide a project schedule with key milestones identified, power shutdown requirements, and completion dates. Contractor to coordinate any shutdown period with Physical Plant. The contractor is required to provide temp power using portable generators to the buildings affected by the shutdown. However, the Switchgear building construction can resume until November. All open trenches that fall within the Oval Driveway path and parking drive lanes must be metal-plated to ensure safe traffic. A Flagger must be present during construction to direct traffic during excavation work when any of the lane/s is closed during business hours; detour and construction sign/s shall be located. The Grawemeyer Hall Parking area must be available for use by the occupants of Grawemeyer Hall and surrounding buildings. Cover work-in-place for accessibility. A 48-hour notice is required from Belknap Work Control for work within the Grawemeyer Hall parking area that would restrict or prohibit parking.

Key dates

Questions due
Dec 7, 2026, 2:00 PM Eastern Time
Pre-bid meeting
Dec 1, 2026, 1:00 PM Eastern Time · Mandatory
Bids due
Jan 5, 2027

Documents

  • IB__1209010_Grawemeyer_Switchgear_Replacement_and_New_Building.pdf24 pages
  • Exhibit_O_Workers_Comp_Affidavit.docx
  • Exhibit_N_Payment_and_Performance_Bond_Template.docx
  • Exhibit_M_Sample_Contract_for_reference_only_.pdf39 pages
  • Exhibit_L_Unit_Pricing.pdf
  • Exhibit_K_Alternates.pdf1 pages
  • Exhibit_J_Cost_Breakout_Worksheet.pdf1 pages
  • Exhibit_I_Electrical_Pre-Purchased_Submittals.pdf

8 more files

See all documents · Download with Pro

Similar bids near Louisville

Closing soon near Louisville