Jones Ferry Road WTP Rapid Mix Improvements

Orange Water & Sewer AuthorityNorth Carolina#460-272-55 A

The work includes full installation, integration, and commissioning. A mandatory pre-bid conference is scheduled for November 19, 2026, at 10:30 A.M. in Carrboro. Bids are due by 3:00 P.M. on December 3, 2026, at the Boardroom, 400 Jones Ferry Road, Carrboro, NC. A 5% bid deposit or Bid Bond is required. The project must achieve Substantial Completion within 410 days and Final Completion within 450 days from the Administrative Notice to Proceed. Bidders must submit a Non-Collusion Affidavit and email the Engineer to receive Addenda.

On PublicBidSearch: the original bid posting, 5 bid documents and the agency contact (name and email) for this bid.

Open Original Bid Source Pro

Contact

Agency contact for this bidName and email — included with ProPro

Overview

Due
Dec 3, 2026
Time stated in bid documents
Dec 3, 2026, 3:00 PM Eastern Time
Bid bond
5%
Submission
mail, hand delivery
Documents analyzed
5

Scope of work

  • Replace seven 24-inch butterfly valves
  • Install six slide gates
  • Install polymer application point
  • Complete and operable system integration

Steps to Bid

  1. 1

    Register and confirm interest by emailing [email available with Pro] to receive Addenda and updates.

  2. 2

    Review the full Bidding Documents online at Official linkPro, beginning October 26, 2026. was Oct 26, 2026

    This date has passed — confirm eligibility with the agency before bidding.

  3. 3

    Attend the mandatory Pre-Bid Conference on November 19, 2026, at 10:30 A.M. local time, at the Boardroom, 400 Jones Ferry Road, Carrboro, NC. was Nov 19, 2026, 10:30 AM

    This date has passed — confirm eligibility with the agency before bidding.

  4. 4

    Submit a Non-Collusion Affidavit as required by North Carolina General Statute 133-30. by Dec 3, 2026, 3:00 PM

What you'll need

Contract duration

410 consecutive calendar days from the date of Administrative Notice to Proceed

Submission

Mail, Hand delivery

NAICS

237130

Pursuit snapshot

Pro
  • Go / no-go verdict on every requirement
  • 5 watch-outs that disqualify bidders
Unlock with Pro — $20/mo

Cancel anytime · no card to browse

Project details

The Project consists of furnishing all materials, labor, equipment, tools, and associated appurtenances for the complete and operable installation of: seven 24-inch butterfly valves, six slide gates, and a polymer application point, as described in the Specifications and shown on the Drawings. The scope includes all work necessary to complete the installation, including but not limited to site preparation, equipment removal, new equipment installation, integration with existing systems, and commissioning. The Bid shall remain irrevocable for 90 calendar days after the bid opening. Bidders must email [email available with Pro] to be added to the Addenda distribution list.

Key dates

Pre-bid meeting
Nov 19, 2026, 10:30 AM Eastern Time
Bids due
Dec 3, 2026

Documents

  • 00_11_16_-_Advertisement_for_Bids.pdf3 pages
  • 00-11-16-Advertisement-for-Bids-1.pdf3 pages
  • 00_11_16_-_Advertisement_for_Bids_Jones_Ferry_Road_WTP_Rapid_Mix_Improvement.pdf3 pages
  • 00-11-16-Advertisement-for-Bids-2.pdf3 pages
  • OWASA-Rapid-Mix-Improvements_Addendum-1.pdf6 pages

See all documents · Download with Pro

Similar open bids

Closing this week nearby