Seaplane Haul-Out Ramp Refurbishment at Ketchikan Airport
Alaska Department of Transportation & Public Facilities — Southcoast RegionKetchikan, Ketchikan Gateway, Alaska#SFAPT00327
The Alaska Department of Transportation & Public Facilities is soliciting bids to remove and replace the seaplane haul-out ramp at Ketchikan Airport. The project is valued between $1M and $2.5M, located in Ketchikan, AK. Bidders must be qualified for heavy construction work and capable of meeting FAA and state aviation standards.
Awarded to Logjam Construction LLC
On PublicBidSearch: the original bid posting, 1 bid document and the agency contact (name, email and phone) for this bid.
Contact
Agency contact for this bidName, email and phone — included with ProProOverview
- Due
- Aug 21, 2026
- Time stated in bid documents
- Aug 21, 2026, 3:00 PM Alaska Time
- Bid bond
- 10%
- Performance bond
- 100%
- Payment bond
- 100%
- Submission
- mail, hand delivery
- Contract term
- 120 calendar days
- Required submission items
- 4 items · full checklist with Pro
Scope of work
- Install new concrete and steel support system
- Reinstate drainage and erosion control systems
- Surface with FAA-compliant materials
- Complete within 120 days of Notice to Proceed
Steps to Bid
- 1
Register with the Alaska Department of Transportation & Public Facilities procurement portal.
- 2
Review the full solicitation and technical specifications available at Official linkPro.
- 3
Submit a complete bid package by 3:00 PM AKT on Friday, August 21, 2026. was Aug 21, 2026, 3:00 PM
This date has passed — confirm eligibility with the agency before bidding.
What you'll need
Insurance
RequiredGeneral Liability: $1M per occurrence / $2M aggregate. Workers’ Compensation: Statutory limits. Umbrella: $2M.
Prequalification
Not requiredContract duration
120 calendar days from Notice to Proceed
Award method
Lowest Responsible Bidder
Submission
Mail, Hand delivery
NAICS
237130
How to submit
Submit one original and one electronic copy (PDF) in a sealed envelope. Include all required forms, bid bond, and compliance documents. Electronic submission via portal is not accepted. All submissions must be received by 3:00 PM AKT on August 21, 2026.
Get alerts for bids like this
New construction bids in Alaska
This bid has closed. We'll tell you when the next one like it posts. Free, no card needed.
Get alerts — freeProject details
Work includes demolition of the current ramp structure, site preparation, installation of new structural components, and surfacing to meet FAA and Aeronautics standards. Project is located in Ketchikan, Ketchikan Gateway Borough, Alaska. Estimated value between $1,000,000 and $2,500,000. Federal funding via AIP 3-02-0144-040-2026. Construction scope under the Alaska Department of Transportation & Public Facilities, Southcoast Region.
Documents
- proposal
More from this agency
- Morris Thompson Center and Lavery Transportation Enhancement (CMAQ/CRP) · closes Dec 1, 2026
- ANC Vertical Infrastructure Earthquake Repairs · closes Dec 2, 2026
- Statewide Bridge Navigational Light Improvements · closes Dec 3, 2026
- Noatak Airport Relocation · closes Dec 3, 2026
- Rehabilitation of Aprons at Gates B1, B3, and B5, Ted Stevens Anchorage International Airport · closes Dec 9, 2026
Similar bids near Ketchikan
- Submarine Cable Installation and Maintenance · Ketchikan · closes Dec 1, 2026
Closing soon near Ketchikan
- Ketchikan Tunnel Valves · Ketchikan · closes Nov 30, 2026
- Second Avenue Reconstruction Design · Ketchikan · closes Dec 2, 2026
- Port Capital Improvements - Phase I · Ketchikan · closes Dec 4, 2026