OpenConstructionCloses Dec 16, 2026

Siding Replacement - Building B at State Aided Development: Woodland Meadows (667-1 & 667-2)

Norton Housing AuthorityMassachusetts

The Norton Housing Authority is soliciting sealed electronic bids for the siding replacement at Building B, Woodland Meadows, Norton, MA. Scope includes removal of existing wood siding and trim, installation of new fiber cement siding with rigid insulation and PVC trim, replacement of wood railings with aluminum systems, and temporary relocation of electrical, HVAC, and fire alarm equipment. Bids must be submitted electronically by 16 December 2026 at 1:00 PM EST. A 5% bid deposit is required. Workforce participation benchmarks are 6.9% women and 15.3% minorities. A pre-bid site visit is mandatory on 12/02/2026 at 10:30 AM EST at 120 West Main Street, Norton, MA. Contract documents are available at [link available with Pro].

On PublicBidSearch: the newspaper notice and the agency contact (name, email and phone) for this bid.

Open Newspaper Notice Pro

Contact

Agency contact for this bidName, email and phone — included with ProPro

Overview

Due
Dec 16, 2026
Time stated in bid documents
Dec 16, 2026, 1:00 PM Eastern Time
Bid bond
5%
Submission
online portal
Required submission items
2 items · full checklist with Pro

Scope of work

  • Remove existing texture 1-11 wood siding at Building B
  • Install new fiber cement siding with rigid insulation and weather barrier
  • Replace wood railings with new aluminum railing system
  • Temporarily remove and reinstall surface-mounted electrical and HVAC equipment

Steps to Bid

  1. 1

    Register as an electronic bidder on Official linkPro

  2. 2

    Review and download contract documents from Official linkPro

  3. 3

    Submit all required documents and bid electronically via Official linkPro by Dec 16, 2026, 1:00 PM

  4. 4

    Attend the mandatory pre-bid site visit on 12/02/2026 at 10:30 AM EST at 120 West Main Street, Norton, MA by Dec 2, 2026, 10:30 AM

  5. 5

    Submit RFI requests online by 12/07/2026 at 5:00 PM EST by Dec 7, 2026, 5:00 PM

What you'll need

Insurance

Required

Bids are subject to M.G.L. c.149 §44A-J & to minimum wage rates as required by M.G.L. c.149 §§26 to 27H inclusive.

Submission

Online portal

NAICS

236220

How to submit

All bids must be submitted electronically via Official linkPro. Bidders must register as electronic bidders prior to submission. Bid forms and contract documents are available for download at Official linkPro. Hard copy bids will not be accepted.

Pursuit snapshot

Pro
  • Go / no-go verdict on every requirement
  • 5 watch-outs that disqualify bidders
  • The 2-item required-submittals checklist
Unlock with Pro — $20/mo

Cancel anytime · no card to browse

Project details

The Norton Housing Authority, the Awarding Authority, invites sealed bids from contractors for the Siding Replacement - Building B at State Aided Development: Woodland Meadows (667-1 & 667-2), located in Norton, Massachusetts. The project includes removal of existing texture 1-11 wood wall siding at Building B within the Woodland development, with existing sheathing to remain. All existing trim shall be removed and replaced with new PVC trim throughout. The new siding assembly will consist of rigid insulation, weather barrier, wood furring/strapping, and factory-finished fiber cement vertical panels. Temporary removal and reinstallation of all existing surface-mounted electrical and HVAC equipment is the contractor’s responsibility. The contractor must coordinate the removal and reinstallation of all surface-mounted fire alarm equipment with the Housing Authority’s vendor. The work is estimated to cost $323,868.93. This project is being electronically bid; hard copy bids will not be accepted. Bids must be submitted online at [link available with Pro] and received no later than 16 December 2026 at 1:00 PM EST. General bids must be accompanied by a bid deposit of not less than 5% of the greatest possible bid amount (including all alternates), payable to the Norton Housing Authority. The project is subject to M.G.L. c.149 §44A-J and minimum wage rates as required by M.G.L. c.149 §§26 to 27H inclusive. Requests for waivers must be submitted to Chad Howard ([email available with Pro]) at least 5 calendar days prior to the general bid date. c.149 §44A(2)(G). Potential bidders shall meet outside the Community Building within the Woodland Meadows development. The project is advertised under M.G.L.

Key dates

Questions due
Dec 7, 2026, 5:00 PM Eastern Time
Pre-bid meeting
Dec 2, 2026, 10:30 AM Eastern Time
Site visit
Dec 2, 2026, 10:30 AM Eastern Time
Bids due
Dec 16, 2026