OpenIFBCloses Nov 24, 2026

Telford Hall Exterior Facade Repairs

Eastern Kentucky UniversityRichmond, Madison, Kentucky#CITB-538-2027

Eastern Kentucky University is soliciting bids for the repair and replacement of spalling concrete on the exterior facade of Telford Hall in Richmond, KY. The scope includes demolition and replacement of all existing concrete paving, curbs, aprons, and ramps in the project area with new 6-inch-thick vehicular-rated concrete, reinforced with #4 rebar at 12-inch centers, and finished with a light broom finish. All exposed rebar must be treated with rust inhibitor and primer. Expansion joints are to be sealed with SikaFlex NP 1 on vertical surfaces. The contractor must field-verify all existing conditions, obtain all permits, install erosion control, and restore all damaged adjacent areas. A mandatory pre-bid meeting is required at the worksite on November 17, 2026, at 2:00 PM EST. Bids must be submitted electronically by November 24, 2026, at 2:30 PM EST. Bid, performance, and payment bonds are required. The contractor must be registered in EKU’s e-procurement system. The project must be substantially completed within 30 days and fully completed within 45 days of the purchase order start date. The estimated value is $133,000.00.

On PublicBidSearch: the original bid posting, 8 bid documents and the agency contact (name and email) for this bid.

Open Original Bid Source Pro

Contact

Agency contact for this bidName and email — included with ProPro

Overview

Due
Nov 24, 2026
Time stated in bid documents
Nov 24, 2026, 2:30 PM Eastern Time
Performance bond
100%
Payment bond
100%
Submission
electronic portal
Documents analyzed
8 published · 6 analyzed

Scope of work

  • Demolish and replace all concrete paving, curbs, aprons, ramps, and walkway features
  • Install chain-link fencing to restrict traffic and maintain building access
  • Restore damaged adjacent areas including sod, planting beds, and grass

Steps to Bid

  1. 1

    Register in EKU's e-procurement system

  2. 2

    Attend the mandatory pre-bid meeting at Telford Hall on November 17, 2026, at 2:00 PM EST was Nov 17, 2026, 2:00 PM

    This date has passed — confirm eligibility with the agency before bidding.

  3. 3

    Submit questions by November 18, 2026, at 2:00 PM EST via the Q&A Board in the Jaggaer system was Nov 18, 2026, 2:00 PM

    This date has passed — confirm eligibility with the agency before bidding.

What you'll need

Contract duration

30 days from purchase order start date for substantial completion; 45 days for final completion

Submission

Electronic portal

NAICS

236220

How to submit

Submit electronically via the Jaggaer e-procurement system. All required documents must be uploaded and signed. Bidders must acknowledge any addenda issued after submission by re-uploading the bid with the addendum acknowledgment.

Pursuit snapshot

Pro
  • Go / no-go verdict on every requirement
  • 5 watch-outs that disqualify bidders
Unlock with Pro — $20/mo

Cancel anytime · no card to browse

Project details

The new concrete shall have a light broom finish, contrasted broom finish to visually separate panel sections, and include isolation joints at junctions with walls and control joints following existing patterns. Joint sealant work includes full-width caulking of affected panels. The contractor must be registered in EKU’s e-procurement system prior to bidding.

Key dates

Pre-bid meeting
Nov 17, 2026, 2:00 PM Eastern Time
Bids due
Nov 24, 2026

Documents

  • 1471044-1775258118Campus_Map.pdf1 pages
  • 1471044-2128681581Proposal_Agreement.pdf1 pages
  • 1471044-212868163310455_Bid_Drawings.pdf2 pages
  • 1471044-212868167310455_Project_Manual.pdf
  • 1471044-2128682522Submit_Review_Acknowledgement_Checklist.pdf1 pages
  • 1471044-2128682162List_of_Unit_Prices.pdf1 pages
  • 1471044-2128682165Handbook_Acknowledgment.pdf1 pages
  • 1471044-event.pdf8 pages

See all documents · Download with Pro

More from this agency

Similar open bids

Closing this week nearby