The project includes new buildings (Headworks, Post Treatment, Biosolids Complex, Operations, and Maintenance Building), a 0.75 MG sludge storage tank, demolition of existing facilities, site civil works, electrical systems (including SCADA and generator), and HVAC/plumbing. The base bid must be substantially completed by June 1, 2029, and fully completed by November 1, 2029. If Bid Alternate A is selected, completion dates are extended to April 1, 2030, and July 1, 2030. A pre-bid conference is scheduled for December 2, 2026, at 1:00 PM, at The Shores at Five Island, 14 N Lawler St., Emmetsburg, IA. Attendance is encouraged but not required. Bidding documents are available at [link available with Pro]. The project is subject to BABAA requirements with de minimis, small grants, and minor components waivers. The owner may reject any or all bids.

On PublicBidSearch: the original bid posting, 1 bid document and the agency contact (name only) for this bid.

Open Original Bid Source Pro

Contact

Agency contact for this bidName only — included with ProPro

Overview

Due
Dec 17, 2026, 1:00 PM CT
Time stated in bid documents
Dec 17, 2026, 1:00 PM Central Time
Submission
mail, hand delivery
Documents analyzed
1
Required submission items
2 items · full checklist with Pro

Scope of work

  • Construct new Headworks Building with screening and grit removal systems
  • Install four-cell Sequencing Batch Reactor (SBR) treatment process
  • Build new Post Treatment Building with tertiary filters and UV disinfection
  • Construct Biosolids Complex Building with rotary drum thickener
  • Install 0.75 MG pre-stressed concrete sludge storage tank

Steps to Bid

  1. 1

    Register as a plan holder on the designated website: Official linkPro

  2. 2

    Obtain the Bidding Documents from the designated website or at the Issuing Office (McClure Engineering Company, 705 1st Ave N, Fort Dodge, IA 50501) during business hours (8:00 AM – 4:00 PM, Monday–Friday).

  3. 3

    Ensure the bid includes a fully completed Bidder Status Form. Failure to submit it may result in the proposal being deemed nonresponsive and rejected. by Dec 17, 2026, 1:00 PM

What you'll need

Contract duration

Substantial completion by June 1, 2029; final completion by November 1, 2029. If Bid Alternate A is selected, substantial completion by June 1, 2029, Bid Alternate A by April 1, 2030, and final completion by July 1, 2030.

Submission

Mail, Hand delivery

NAICS

237130, 237199, 237990

Pursuit snapshot

Pro
  • Go / no-go verdict on every requirement
  • 2 watch-outs that disqualify bidders
  • The 2-item required-submittals checklist
Unlock with Pro — $20/mo

Cancel anytime · no card to browse

Project details

The project includes construction of a new Headworks Building (pre-cast concrete) with mechanically cleaned stair screen, screenings washing and compactor, stacked tray grit removal, grit washing, and submersible raw wastewater influent pumps; a new four-cell Sequencing Batch Reactor (SBR) treatment process; a new Post Treatment Building (pre-cast concrete) with tertiary filters (pile cloth) and UV disinfection; a new Biosolids Complex Building (pre-cast concrete) with rotary drum thickener and sludge pumping; a new 0.75 million gallon (MG) sludge storage tank (pre-stressed concrete); a new Operations Building (pre-engineered metal building) with blowers (rotary screw), air compressors, compressed air storage tanks, electrical room, mechanical room, lab and control room, and locker room facilities; a new Maintenance Building (Bid Alternate A), a pre-engineered metal building; demolition of existing plant facilities and structures; site grading, paving, structure excavation, underground utilities, and other site civil works; electrical work including a new stand-by generator, power and controls, and a new SCADA system; HVAC and plumbing work for all new buildings; and all other work as required by the plans and specifications. The base bid must be substantially completed by June 1, 2029, and ready for final payment by November 1, 2029. Failure to meet any substantial completion date results in liquidated damages of $1,100 per calendar day. Failure to meet any final completion date results in liquidated damages of $3,800 per calendar day. Prospective bidders must register as plan holders. A resident bidder preference may apply under Iowa law.

Key dates

Pre-bid meeting
Dec 2, 2026, 1:00 PM Central Time
Bids due
Dec 17, 2026, 1:00 PM CT

Documents

  • 0002-20261112-72f087a7f62c1f7a929ecf79a4d5da07.pdf3 pages

See all documents · Download with Pro

Similar bids near Emmetsburg

Closing soon near Emmetsburg