Fire Protection Pumps No. 3 and 4 Rebuild at Jones Island Water Reclamation Facility
Milwaukee Metropolitan Sewerage District — Office of Contract ComplianceMilwaukee, Wisconsin#J06106C11
3 and 4 at the Jones Island Water Reclamation Facility. Work includes disassembly, reverse-engineering, fabrication, repair, reinstallation, and testing. Bids must be submitted electronically via Quest CDN by 2:00 p.m. on December 17, 2026. A pre-bid presentation is available by November 27, 2026. A site tour is scheduled for December 10, 2026, at 9:00 a.m., with pre-registration required. The contract duration is 300 days from the Notice to Proceed. Liquidated damages are $100 per day for delays and $300 per day for missed milestones.
On PublicBidSearch: the newspaper notice, 4 bid documents and the agency contact (name, email and phone) for this bid.
Contact
Agency contact for this bidName, email and phone — included with ProProOverview
- Due
- Dec 17, 2026, 2:00 PM CT
- Time stated in bid documents
- Dec 17, 2026, 2:00 PM Central Time
- Submission
- electronic portal
- Contract term
- 300 days from the Notice to Proceed
- Documents analyzed
- 4 published · 3 analyzed
Scope of work
- Rebuild Fire Protection Pumps No. 3 and 4 at Jones Island Water Reclamation Facility
- Remove pumps and transport to contractor's facility
- Disassemble pumps and remove defective parts
- Reverse-engineer existing components
- Fabricate and install replacement components
- Ship repaired pumps back to JIWRF
Steps to Bid
- 1
Register and purchase the Contract Documents on Quest CDN for $42.00 to become a Plan Holder.
- 2
Review the pre-bid presentation posted on the MMSD website and Quest CDN by 5:00 p.m. on November 27, 2026. was Nov 27, 2026, 5:00 PM
This date has passed — confirm eligibility with the agency before bidding.
- 3
Attend the site tour on December 10, 2026, at 9:00 a.m., and pre-register by contacting Nathan Churchill at [email available with Pro]. by Dec 10, 2026, 9:00 AM
- 4
Submit the bid electronically via Quest CDN at Official linkPro by 2:00 p.m. on December 17, 2026. by Dec 17, 2026, 2:00 PM
What you'll need
Contract duration
300 calendar days from the Notice to Proceed
Submission
Electronic portal
NAICS
333610
Pursuit snapshot
Pro- Go / no-go verdict on every requirement
- 6 watch-outs that disqualify bidders
Cancel anytime · no card to browse
Project details
The work includes: removal of the pumps and transportation to the contractor’s facility; disassembly and removal of defective parts; reverse-engineering of existing components; fabrication and installation of replacement components; shipping of the repaired pump back to JIWRF; reinstallation with all required connections; and startup, functional, and operational test runs. The project is located in Milwaukee, Wisconsin. Bids must be submitted electronically via Quest Construction Data Network (Quest CDN) at [link available with Pro]. Attendance requires pre-registration by contacting Nathan Churchill at [email available with Pro]. The Contract Documents are available for free viewing on Quest CDN; to download plans, contractors must register and purchase the documents for $42.00. Bidders must comply with Small Business Enterprise (SBE) requirements, local workforce participation, and apprenticeship utilization. Liquidated damages are $100 per day for delays beyond the contract completion date and $300 per day for missed interim milestones. The Owner reserves the right to reject all or any non-conforming bids.
Key dates
- Questions due
- Dec 10, 2026
- Site visit
- Dec 10, 2026, 9:00 AM Central Time
- Bids due
- Dec 17, 2026, 2:00 PM CT
Documents
- J06106C11_Invitation_to_Bid_20261117133803_1202.pdf3 pages
- d.asp
- J06106C11_Pre-Bid_Presentation_Slide_Deck_20261117133802_6820.pdf22 pages
- tdr-2026-11-18-0-001_09.pdf1 pages
More from this agency
- Engineering Services – Dryer Train Overhaul and Upgrades at Jones Island Water Reclamation Facility · closes Dec 23, 2026
- Native Landscape Contractor for Green Infrastructure · closes Feb 18, 2028
- Native Landscape Contractor Prequalification · closes Feb 18, 2028
- Native Landscape Contractor for Watercourse & Land Stewardship · closes Feb 18, 2028
- Engineering Services Structural Analysis and Design at South Shore S06049D01
Closing soon near Milwaukee
- 1675 N 121st St, Wauwatosa — Tax-Foreclosed Property Sale via Invitation to Bid · Milwaukee · closes Dec 2, 2026
- 1606 18th Ave, South Milwaukee · Milwaukee · closes Dec 2, 2026
- ITB-ED2612: 6124 W Madison St, West Allis — Tax-Foreclosed Property Sale · Milwaukee · closes Dec 2, 2026
- Vendor Contract for Blauer Jackets · Milwaukee · closes Dec 3, 2026
- Custodial Bank Services · Milwaukee · closes Dec 4, 2026