Heat Shift Chillers - UMass Boston - Trade RFQ at UMass Boston
UMass Building AuthorityBoston, Massachusetts#24-B2
c. 149A. The RFQ is the first phase; only firms achieving a minimum of 70 total points across management experience, references, and capacity will be invited to bid. The project involves replacing heat load in the existing Central Utility Plant by installing three new heat shift chillers. The HVAC trade is estimated at $8.4M and Electrical at $2.25M. Bidders must submit a complete SOQ package electronically by 2:00 PM EST on December 9, 2026. Questions must be submitted by November 30, 2026. The process is not open to the public; SOQs are not read publicly.
On PublicBidSearch: the original bid posting, 1 bid document and the agency contact (name and email) for this bid.
Contact
Agency contact for this bidName and email — included with ProProOverview
- Due
- Dec 9, 2026
- Time stated in bid documents
- Dec 9, 2026, 2:00 PM Eastern Time
- Bid bond
- 110%
- Submission
- Documents analyzed
- 1
Scope of work
- Replace one (1) existing boiler and one (1) existing chiller
- Integrate new chiller technology into the existing plant infrastructure
- Oversee rigging and setting of equipment at the job site
Steps to Bid
- 1
4
Submit one complete electronic copy of the SOQ Application Package in PDF format via email to [email available with Pro]. The email must be sent only to this address.
- 2
5
The email subject line must be: '24-B2 Trade (for which submission is made: masonry, electrical) SOQ - Company Name'. The body of the email must include: 'SOQ for Trade Contractor Services; Project No: 24-B2 Heat Shift Chillers; Trade for Which Submission is Made: (i.e. masonry, electrical); Respondent Trade Contractor’s Name; Respondent Trade Contractor’s Address; Respondent Trade Contractor’s Telephone Number; Respondent Trade Contractor’s Contact Person and Email Address.'
- 3
7
Submit questions to Collin Sabin at [email available with Pro] by 12:00 PM on November 30, 2026. Questions must be submitted by email only.
What you'll need
Contract duration
15 months from the Notice to Proceed
Submission
NAICS
238210, 238220
Pursuit snapshot
Pro- Go / no-go verdict on every requirement
- 3 watch-outs that disqualify bidders
Cancel anytime · no card to browse
Project details
Work will be performed within the existing operating plant. The RFQ is the first phase of a two-phase procurement process under M.G.L. c. The estimated total project construction cost is $14,500,000, with an estimated duration of 15 months. The HVAC trade is estimated at $8,400,000 and the Electrical trade at $2,250,000. The RFQ is not an invitation to bid. The submission must include completed forms and schedules, supporting documentation, and a commitment letter for bonding in the amount of 110% of the estimated trade contract value. Questions must be submitted by email to Collin Sabin at [email available with Pro] by 12:00 PM on November 30, 2026. Responses will be posted on the UMassBA website by 5:00 PM on December 3, 2026.
Key dates
- Questions due
- Nov 30, 2026, 12:00 PM Eastern Time
- Bids due
- Dec 9, 2026
Documents
- 24-b2-rfq-c.149a-trade-contractor-final-261117.pdf46 pages
Similar bids near Boston
- Request for Qualifications: University of Massachusetts Boston Campus Heat Shift Chillers · Boston · closes Dec 9, 2026
- 12 Channel HVAC Maintenance · Boston · closes Dec 14, 2026
- 12 Channel Streece HVAC Maintenance · Boston · closes Dec 14, 2026
- McCormack AHU Upgrades Phase 1 & 2 · Boston · closes Dec 2, 2026
- Request for Proposals for Mechanical, Regenerative Air, and Vacuum Street Sweepers — GBPC-2027 · Boston · closes Dec 10, 2026
Closing soon near Boston
- Notice of Proposed Best Value Grant Award - Massachusetts Woodlands Institute · Suffolk County · closes Nov 30, 2026
- Installation of the Physical Security Infrastructure for Parcels C1 and C2a Lots · Boston · closes Dec 1, 2026
- Installation of HD Shelving, Loading Dock Lift, Roof Replacement, and Signage at 201 Rivermoor Street, West Roxbury, MA · Boston · closes Dec 2, 2026
- IFB 2027-277 Central Fire Station Apparatus Floor Replacement Phase 1 · Suffolk County · closes Dec 3, 2026
- Worcester Area Interoperability System Upgrades · Boston · closes Dec 4, 2026