OpenIFBCloses Jan 20, 2027

Invitation for Bids: 115 kV/12.47 kV, 15/20/25/28 MVA Power Transformer for Jorstad Substation

Mason County PUDWashington

Public Utility District No. 1 of Mason County, Washington, is soliciting sealed bids for a 115 kV/12.47 kV, 15/20/25/28 MVA power transformer for the Jorstad Substation. Bidders must be qualified manufacturers or authorized distributors. Bid documents are available online or for a $250 nonrefundable fee. Questions must be submitted by 3:00 p.m. PST on January 13, 2027. Bids must be received by 3:00 p.m. PST on January 20, 2027, at the District office in Shelton, WA. Submissions may be delivered by mail, courier, or hand delivery. Bids will be opened publicly at 3:15 p.m. PST on the same day via Zoom.

On PublicBidSearch: the newspaper notice for this bid.

Open Newspaper Notice Pro

Overview

Due
Jan 20, 2027
Time stated in bid documents
Jan 20, 2027, 3:00 PM Pacific Time
Submission
mail, courier, hand delivery

Steps to Bid

  1. 1

    1

    Review the RFP Attachment A, Material Specification MPUD-13-01-00, available on the District's website at [link available with Pro] or as a hard copy for $250 nonrefundable fee.

  2. 2

    2

    Submit questions by 3:00 p.m. PST on January 13, 2027, for inclusion in an addendum.

  3. 3

    3

    Prepare a sealed bid marked 'Bid Documents Jorstad Substation Power Transformer'.

  4. 4

    4

    Deliver the bid by 3:00 p.m. PST on January 20, 2027, to the District office at 21971 N. US Hwy 101, Shelton, WA 98584, via mail, courier, or hand delivery.

  5. 5

    5

    Attend the public bid opening at 3:15 p.m. PST on January 20, 2027, via Zoom at [link available with Pro].

What you'll need

Submission

Mail, Courier, Hand delivery

NAICS

335912, 335913

How to submit

Bids must be sealed, marked 'Bid Documents Jorstad Substation Power Transformer', and delivered to the District office by 3:00 p.m. PST on January 20, 2027.

In person/mail: 21971 N. US Hwy 101, Shelton, WA 98584

Pursuit snapshot

Pro
  • Go / no-go verdict on every requirement
  • 3 watch-outs that disqualify bidders
Unlock with Pro — $20/mo

Cancel anytime · no card to browse

Project details

Bid documents are available beginning November 23, 2026, on the District's website at [link available with Pro] or as a hard copy for a $250 nonrefundable fee. Final addenda will be issued on January 15, 2027. The District is not responsible for late delivery. PUD 1 is an equal opportunity provider and employer.

Key dates

Questions due
Jan 13, 2027, 3:00 PM Pacific Time
Bids due
Jan 20, 2027

Similar bids in Washington

Closing soon in Washington