OpenConstructionCloses Dec 11, 2026

Fitchburg Road Sewer Main Extension – Phase 1 Project

Town of AyerAyer, Massachusetts

The Town of Ayer is soliciting sealed bids for the construction of a new gravity sewer main on Fitchburg Road, including appurtenances, service connections, trench paving, and full traffic management and road restoration per MassDOT standards. Work must be completed within 150 calendar days after the Notice to Proceed, which will be issued no earlier than April 1, 2027. Bids are due at the Ayer DPW Administrative Building, 25 Brook Street, Ayer, MA 01432, by 2:00 PM on December 11, 2026. Each bid must include a 5% bid security. The successful bidder must provide 100% performance and payment bonds. Prevailing wage rates under M.G.L. Chapter 149 apply. The solicitation is governed by M.G.L. Chapter 30, Section 39M.

On PublicBidSearch: the newspaper notice for this bid.

Open Newspaper Notice Pro

Overview

Due
Dec 11, 2026
Bid bond
5%
Performance bond
100%
Payment bond
100%
Submission
mail, hand delivery
Required submission items
1 items · full checklist with Pro

Scope of work

  • Pave trenches and restore road surface
  • Implement traffic management and MassDOT-compliant road restoration

Steps to Bid

  1. 1

    Review the full bid documents available at Official linkPro.

  2. 2

    Submit a sealed bid to the Ayer DPW Administrative Building at 25 Brook Street, Ayer, MA 01432, by 2:00 PM on December 11, 2026.

  3. 3

    Ensure the bid is accompanied by a bid security equal to 5% of the bid amount.

  4. 4

    The bidder must not withdraw their bid for 60 days after the opening, excluding weekends and legal holidays.

What you'll need

Contract duration

150 calendar days from the Notice to Proceed

Submission

Mail, Hand delivery

NAICS

237130

How to submit

Bids must be sealed and submitted in person or by mail to the Ayer DPW Administrative Building at 25 Brook Street, Ayer, MA 01432. Each bid must include a bid security equal to 5% of the bid amount. Bids will be publicly opened and read aloud at 2:00 PM on December 11, 2026.

In person/mail: 25 Brook Street, Ayer, MA 01432

Pursuit snapshot

Pro
  • Go / no-go verdict on every requirement
  • 4 watch-outs that disqualify bidders
  • The 1-item required-submittals checklist
Unlock with Pro — $20/mo

Cancel anytime · no card to browse

Project details

The Town of Ayer DPW is seeking sealed bids from general contractors for the construction of the Fitchburg Road Sewer Main Extension – Phase 1 project. The work includes constructing a new gravity sewer main on Fitchburg Road, installing appurtenances, making service connections, paving trenches, and performing all required traffic management and road restoration in compliance with MassDOT standards and permit requirements. Bids will be publicly opened and read aloud at that time and place. Each bid must be accompanied by a bid security equal to 5% of the bid amount. No bidder may withdraw their bid for 60 days after the opening, excluding Saturdays, Sundays, and legal holidays. The bidding and award process will follow M.G.L. Chapter 30, Section 39M. Electronic copies of the contract documents are available at [link available with Pro].

Key dates

Bids due
Dec 11, 2026