LS 16, 17 & 18 Upgrades
Alderwood Water & Wastewater DistrictLynnwood, Washington#S2004
Alderwood Water & Wastewater District is soliciting bids for the Lift Stations 16, 17 & 18 Upgrades project (Contract Number S2004A). The project includes the construction of three new lift stations with associated wet wells, vaults, piping, pumps, motors, electrical, instrumentation, and communication systems. It also involves the removal of existing structures, abandonment, demolition, and modifications to existing Lift Station 11A, and the installation of vacuum relief valves on Lift Station 5. The estimated cost for this project is between $10,900,000 and $14,600,000. Bids are due January 7, 2027, at 3:00 P.M. A pre-bid meeting is scheduled for December 18, 2026, at 10:00 A.M. Pacific Standard Time. Bidders are required to submit a bid guaranty of not less than five percent (5%) of the Total Bid Price.
On PublicBidSearch: the original bid posting, 12 bid documents and the agency contact (name only) for this bid.
Contact
Agency contact for this bidName only — included with ProProOverview
- Due
- Jan 7, 2027
- Time stated in bid documents
- Jan 7, 2027, 3:00 PM Pacific Time
- Submission
- mail, hand delivery
- Documents analyzed
- 12 published · 3 analyzed
Scope of work
- Construct duplex submersible sewer Lift Station 16.
- Construct triplex sewer Lift Station 17 with storage facility.
- Construct duplex submersible sewer Lift Station 18.
- Abandon, demolish, and modify existing sewer Lift Station 11A.
- Install three vacuum relief valves on Lift Station 5 force main.
Steps to Bid
- 1
Submit sealed bids to Alderwood Water & Wastewater District at the District’s Administration Building, Attn: Tina Holmes, Contracts Administrator, 3626 156th Street SW, Lynnwood, WA 98087. by Jan 7, 2027, 3:00 PM
Bids received after this date and time will not be considered.
- 2
Attend the pre-bid meeting. by Dec 18, 2026, 10:00 AM
Held in person at the District’s Administration office located at 3626 156th St SW Lynnwood, WA 98087. Attendance is strongly encouraged.
- 3
Submit all questions in writing. by Dec 30, 2026, 2:00 PM
Questions must be submitted no later than this date and time to James Waihenya at [email available with Pro] or by mail.
What you'll need
Submission
Mail, Hand delivery
How to submit
Bids shall be submitted in accordance with the Contract Documents.
In person/mail: Alderwood Water & Wastewater District, Attn: Tina Holmes, Contracts Administrator, 3626 156th Street SW, Lynnwood, WA 98087
Pursuit snapshot
Pro- Go / no-go verdict on every requirement
- 4 watch-outs that disqualify bidders
Cancel anytime · no card to browse
Project details
Removal of remaining above/below grade structures at the site. Construction of a triplex sewer Lift Station 17 on a new site including a building, piping, pumps, motors, underground offline storage facility, electrical, instrumentation, communication and miscellaneous accessories. Installation of 10” HDPE sewer force main and 12” gravity sewer and manholes and placement and restoration of AC pavement. Removal of remaining above/below grade structures at the site.
Key dates
- Questions due
- Dec 30, 2026, 2:00 PM Pacific Time
- Pre-bid meeting
- Dec 18, 2026, 10:00 AM Pacific Time
- Bids due
- Jan 7, 2027
Documents
- S2004A-LS-16-17-18-Advertisement-for-Bid.pdf2 pages
- S2004A_Contract_Documents_with_Appendices_Section-1.pdf
- S2004A_Contract_Documents_with_Appendices_Section-2.pdf
- S2004A_Contract_Documents_with_Appendices_Section-3.pdf36 pages
- S2004A_Bid_Ready_Plans_Part-1.pdf
- S2004A_Bid_Ready_Plans_Part-2.pdf
- S2004A_Bid_Ready_Plans_Part-3.pdf11 pages
- S2004A_Bid_Ready_Plans_Part-4.pdf
4 more files
More from this agency
- S2004A Lift Stations 16, 17 & 18 Upgrades · closes Jan 7, 2027
Similar bids near Lynnwood
- Wastewater Planning and Modeling · Shoreline · closes Dec 2, 2026
- Edison Wastewater Treatment Facility Maintenance & Repair Services · Mount Vernon · closes Dec 7, 2026
Closing soon near Lynnwood
- Hardware, Microsoft Surface & Accessories · Everett · closes Dec 1, 2026
- Request for Qualifications: Recreation, Parks and Open Space Plan (2028–2034) and Park Impact Fee Rate Study · Mountlake Terrace · closes Dec 1, 2026
- NE 68th St Pedestrian and Bicyclist Safety Improvements · Kirkland · closes Dec 2, 2026
- Charles Street Vehicle Maintenance HVAC Improvements · Seattle · closes Dec 2, 2026
- Fuel Tank Testing · Seattle · closes Dec 4, 2026