Downtown Streetscape Improvements along 3rd Avenue SW/5th Street SW in the City of Cullman
CullmanCullman, Alabama#20260406
The City of Cullman, Alabama, is soliciting sealed bids for the construction of downtown streetscape improvements along 3rd Avenue SW/5th Street SW. Bids must be submitted by 2:00 PM local time on December 8, 2026, at the Cullman City Hall Auditorium. Key scope items include removal and replacement of sidewalks, curbs, gutters, and storm drainage. A bid bond of 5% of the bid amount (up to $10,000) is required. Contractors are not required to be licensed to bid, but must provide proof of licensure prior to award. The contractor must perform at least 30% of the work using their own organization. Bid documents are available for purchase from St. John & Associates, Inc., or online at [link available with Pro]. The project is subject to federal regulations, including Davis-Bacon wage requirements and non-discrimination provisions.
On PublicBidSearch: the original bid posting for this bid.
Overview
- Due
- Dec 8, 2026, 2:00 PM CT
- Time stated in bid documents
- Dec 8, 2026, 2:00 PM Central Time
- Bid bond
- 5%
- Submission
- mail, hand delivery
- Required submission items
- 2 items · full checklist with Pro
Scope of work
- Remove 459 sq yd of concrete sidewalk and driveway
- Remove 1,125 lin ft of curb and gutter
- Install 6,926 sq yd of crushed aggregate base
- Pave 940 sq yd with concrete for sidewalks and ramps
- Install 617 lin ft of roadway pipe in various sizes
- Construct 9 storm structures
Steps to Bid
- 1
Obtain bid documents from St. John & Associates, Inc. (508 First Avenue SE, Cullman, AL 35055) for $200.00, payable to St. John & Associates, Inc., or download digitally from Official linkPro for $50.00.
- 2
Prepare and complete a sealed bid proposal, including a bid bond or cashier’s check for 5% of the bid amount (maximum $10,000.00) payable to the City of Cullman.
- 3
Submit the sealed bid proposal in person at the Cullman City Hall Auditorium, 204 Second Avenue NE, Cullman, AL 35055, by 2:00 PM local time on December 8, 2026. by Dec 8, 2026, 2:00 PM
What you'll need
Insurance
RequiredPROOF OF INSURANCE COVERAGES OF THE TYPES AND AMOUNTS AS SET FORTH IN THE PROJECT SPECIFICATIONS WILL BE REQUIRED OF THE CONTRACTOR, AND ANY AND ALL SUBCONTRACTORS, PRIOR TO BEGINNING WORK.
Submission
Mail, Hand delivery
NAICS
237130, 237199
Pursuit snapshot
Pro- Go / no-go verdict on every requirement
- 3 watch-outs that disqualify bidders
- The 2-item required-submittals checklist
Cancel anytime · no card to browse
Project details
TAPAA-TA26(900). Bids will be received at the Cullman City Hall Auditorium, 204 Second Avenue NE, Cullman, AL 35055, until 2:00 PM local time on December 8, 2026, at which time they will be publicly opened. The principal items of work include: 459 square yards of concrete sidewalk and driveway removal; 1,125 linear feet of curb and gutter removal; 6,926 square yards of crushed aggregate base course; 940 square yards of concrete paving for sidewalks, curb ramps, and driveways; 617 linear feet of roadway pipe in various sizes; 9 storm structures; 1,748 linear feet of curb and gutter in various types; one lump sum for decorative lighting; and 147 square yards of brick and concrete sidewalks. A cashier’s check drawn on an Alabama bank or a bid bond for 5% of the amount bid (maximum $10,000.00) and made payable to the City of Cullman must accompany each bid as evidence of good faith. Contractors are not required to be licensed to submit a bid, but must provide proof of all applicable licensures prior to contract award. Proof of insurance coverage as specified in the project specifications will be required of the contractor and all subcontractors prior to beginning work. The contractor must perform at least 30% of the total contract cost using their own organization. Bid documents, including plans and proposals, are available from St. John & Associates, Inc. (508 First Avenue SE, Cullman, AL 35055) upon non-refundable payment of $200.00, payable to St. John & Associates, Inc. Bids may also be mailed upon receipt of payment. Digital copies are available at [link available with Pro] for $50.00 via the 'Planroom' link. Assistance and free registration are available through QuestCDN at (952) 233-1632 or [email available with Pro]. No bid documents will be distributed later than 24 hours prior to the scheduled opening of bids. The project is subject to the Federal Highway Act and related regulations, the Contract Work Hours and Safety Standards Act, and Title VI of the Civil Rights Act of 1964. Minimum wage rates are pre-determined by the Secretary of Labor and are set forth in the advertised specifications. The right to reject any or all bids and to disregard minor irregularities is reserved by the owner.
Key dates
- Bids due
- Dec 8, 2026, 2:00 PM CT
Similar open bids
- Houston County — Roadway Improvements (Widening, Resurfacing, Turn Lane Installation, Crossover Removal, and Traffic… — Alabama Department of Transportation
- 2027 City Wide CIP Sidewalk Repair and Maintenance — City of Mobile
- Saulter Road Sidewalk Connection — City of Homewood
- Pedestrian Improvements to Connect the Aidb Campus to Downtown Talladega — City of Talladega
- Drilling Two 12.5-Foot-Deep, 36-Inch-Diameter Holes Through Rock for Traffic Signal Pole Foundations — Jefferson County, AL - Department of Roads and…
Closing this week nearby
- Westlaw Print Renewal Subscription — closes Nov 20, 2026
- Best Locksets — closes Nov 20, 2026
- Apron Expansion at Evergreen Regional Airport at Middleton Field — closes Nov 20, 2026
- Local Voice and Data Circuits for Redstone Arsenal, AL — closes Nov 20, 2026
- Housekeeping Services for Bryce Hospital, Taylor Hardin Secure Medical Facility, and Mary Starke Harper Geriatric Center — closes Nov 20, 2026