Replacement of Copper Hill Road Bridge Over Mountain Brook

Town of Suffield, CTSuffield, Connecticut

The Town of Suffield, CT is seeking bids for the replacement of the Copper Hill Road Bridge over Mountain Brook. The project involves replacing twin 72-inch corrugated metal pipes with new prestressed concrete deck units, including headwalls, roadway reconstruction, metal beam rail, regrading, and turf restoration. A pre-bid meeting is scheduled for November 17, 2026, at 10:00 AM at the site. Bidders must submit a bid bond or certified check equal to 5% of the base bid. This project is being bid alongside two other bridge projects, and bidders can submit proposals for one, two, or all three, with options for combined project discounts. The contract is subject to state contract compliance and set-aside requirements.

On PublicBidSearch: the original bid posting, 5 bid documents and the agency contact (name and email) for this bid.

Open Original Bid Source Pro

Contact

Agency contact for this bidName and email — included with ProPro

Overview

Due
Dec 3, 2026
Time stated in bid documents
Dec 3, 2026, 2:00 PM Eastern Time
Bid bond
5%
Performance bond
100%
Payment bond
100%
Submission
sealed bid
Documents analyzed
5 published · 2 analyzed

Scope of work

  • Complete replacement of existing twin 72-inch corrugated metal pipes culvert.
  • Installation of cast-in-place concrete headwalls.

Steps to Bid

  1. 1

    Obtain Contract Documents from the Town's website.

  2. 2

    Attend the pre-bid meeting. was Nov 17, 2026, 10:00 AM

    This date has passed — confirm eligibility with the agency before bidding.

    Held at the site.

  3. 3

    Submit sealed bids. by Dec 3, 2026, 2:00 PM

    Received at the Department of Public Works office at the Suffield Town Hall, 83 Mountain Road, Suffield, CT 06078.

What you'll need

Bid security

Required

A satisfactory Bid Bond or Certified Check, in an amount equal to five (5%) of the base Bid, shall be submitted with each bid. The Bid Bond shall be made payable to the Town of Suffield and shall be properly executed by the Bidder and acceptable sureties. All bonds must be from sureties registered in the State of Connecticut. If the Contract is awarded, Owner will give successful Bidder(s) a Notice of Award within sixty (60) days after the day of Bid opening. The successful Bidder(s) shall then execute and deliver to the Owner, within ten (10) days after notification of the award, three (3) executed Agreements, Final Certificate of Insurance, Performance Bond, Payment Bond on forms provided by the Owner. If a successful Bidder fails to comply with the requirements of these documents within ten (10) days of receiving said Notice, that Bidder shall forfeit Bid Security and, at the option of the Owner, the Award may become null and void. The Owner may then proceed to Award the Contract(s)

Contract duration

165 consecutive calendar days of issuance of Notice to Proceed

Award method

The Town will compare individual base bids and discounted combinations and award the projects in the combination that provides the lowest total price from qualified, responsible bidders.

Submission

Sealed bid

How to submit

Bids shall be enclosed in a sealed envelope clearly marked “SEALED BID – TOWN OF SUFFIELD – REPLACEMENT OF COPPER HILL ROAD BRIDGE OVER MOUNTAIN BROOK” along with the name of bidder organization, date and time of bid opening in order to guard against premature opening of the bid. All bids must be submitted on forms supplied by the Owner and shall be subject to all requirements of the Contract Documents, including “Instruction to Bidders”. All bids must be regular in every respect; no interlineations, ditto marks, excisions or special conditions shall be made or included in the bid form by the bidder organization. The blank spaces in the bid must be filled in correctly where indicated for each and every item for which a quantity is given typed or printed in ink. If any price is omitted, the bid may be rejected. The Bidder shall sign his bid correctly. If the bid is made by an individual, his name and post office address must be shown. If made by a firm, partnership, or by a corporation, the bid must be signed by an official of the firm, partnership, or corporation authorized to sign contracts, and also must show the post office address of the firm, partnership or corporation. A Non-Collusion Affidavit shall be completed and returned with the submitted bid.

In person/mail: Department of Public Works office at the Suffield Town Hall, 83 Mountain Road, Suffield, CT 06078

Pursuit snapshot

Pro
  • Go / no-go verdict on every requirement
  • 2 watch-outs that disqualify bidders
Unlock with Pro — $20/mo

Cancel anytime · no card to browse

Project details

The work described above includes furnishing, installing, and incorporating all materials and equipment into the project as well as performing or providing all labor, supervision, equipment, and services unless otherwise noted within the bid documents for the lump sum base bid. Bidders may also offer a fixed dollar deduction for any pair of projects or for all three by completing Section B, Optional Base Bid Deductions, within all of their project proposals. The Contract Documents, including specifications and drawings, may be obtained on the Town’s website. A satisfactory Bid Bond or Certified Check, in an amount equal to five (5%) of the base Bid, shall be submitted with each bid.

Key dates

Pre-bid meeting
Nov 17, 2026, 10:00 AM Eastern Time
Bids due
Dec 3, 2026

Documents

  • 20261105_Bid_Document_CopperHillRoad_Optimized1.pdf230 pages
  • 20261105_CopperHill_FinalPlans1.pdf
  • 20261105_CopperHill_Highway_Standards1.pdf9 pages
  • CopperHill_Addendum_No_1_Accessible.pdf1 pages
  • 20261125CopperHill_Addendum_No_2.pdf13 pages

See all documents · Download with Pro

More from this agency

Similar bids in Connecticut

Closing soon in Connecticut