OpenConstructionCloses Dec 4, 2026, 10:00 AM CT

Grading, drainage, construction of a welded steel girder bridge, lighting and signals, ITS, and paving on I-40 at Christmasville Road (Exit 85) - Madison County

Tennessee Department of Transportation — TDOT Construction DivisionTennessee#CN264076

The project is 0.746 miles long and must be completed by December 31, 2028. Bids are due via the internet (Bid Express) at 10:00 A.M. Central on December 4, 2026. Internet bidding is mandatory. Contractors must be in good standing with the Tennessee Secretary of State. Bidding authorization is obtainable until 4:00 P.M. Central the day before the letting. A $25.00 fee is charged for each bid authorization. The bid must be accompanied by an electronic bid bond in an amount equal to not less than 5% of the bid amount. The successful bidder's check must be in the Department’s possession by 10:00 A.M. Central on the day of the bid opening.

On PublicBidSearch: the original bid posting, 2 bid documents and the agency contact (name, email and phone) for this bid.

Open Original Bid Source Pro

Contact

Agency contact for this bidName, email and phone — included with ProPro

Overview

Due
Dec 4, 2026, 10:00 AM CT
Time stated in bid documents
Dec 4, 2026, 10:00 AM Central Time
Bid bond
5%
Submission
internet
Documents analyzed
2
Required submission items
2 items · full checklist with Pro

Scope of work

  • Construct a welded steel girder bridge on I-40 at Christmasville Road (Exit 85)
  • Perform grading and drainage work on 0.746 miles of I-40
  • Install lighting and traffic signals on I-40 at Christmasville Road
  • Implement Intelligent Transportation Systems (ITS) on I-40 at Christmasville Road
  • Pave 0.746 miles of I-40 at Christmasville Road (Exit 85)

Steps to Bid

  1. 1

    Monitor the Bid Express website for any addenda and acknowledge receipt of all addenda. by Dec 3, 2026, 2:00 PM

  2. 2

    Submit the bid via the internet (Bid Express) by 10:00 A.M. Central on December 4, 2026. by Dec 4, 2026, 10:00 AM

  3. 3

    Ensure the electronic bid bond is submitted via the internet and is in an amount equal to not less than 5% of the bid amount. by Dec 4, 2026, 10:00 AM

What you'll need

Contract duration

On or before 12/31/2028

Submission

Internet

NAICS

237131, 237132, 237133, 237134, 237135, 237136, 237137, 237138, 237139

Pursuit snapshot

Pro
  • Go / no-go verdict on every requirement
  • 5 watch-outs that disqualify bidders
  • The 2-item required-submittals checklist
Unlock with Pro — $20/mo

Cancel anytime · no card to browse

Project details

Contract No. CN264076, Call No. 033 - Madison County Project No. STP-M-NH-I-40-1(372), 57I040-F3-003 (PIN 132680.00): The grading, drainage, construction of a welded steel girder bridge, lighting and signals, ITS, and paving on I-40 at Christmasville Road (Exit 85) (L.M. 17.21 - L.M. 18.02). Completion Time - On or before 12/31/2028 (See Special Provision 108B). If not in good standing on or before 21 days after proposals are opened, the proposal will be rejected. Addenda will be posted on the Bid Express website. Bidders must acknowledge receipt of all addenda and apply any applicable amendments to their electronic bidding file. Failure to do so is grounds for rejection.

Key dates

Questions due
Dec 3, 2026, 2:00 PM Central Time
Bids due
Dec 4, 2026, 10:00 AM CT

Documents

  • 20261204_NoticeToContractors.pdf14 pages
  • 20261204_InstructionsToBidders.pdf4 pages

See all documents · Download with Pro

More from this agency

Similar bids in Tennessee

Closing soon in Tennessee