Joint Outfall F Unit 3A Trunk Sewer Rehabilitation
Sanitation DistrictCalifornia#10394610
2 is seeking bids for the rehabilitation of the Joint Outfall F Unit 3A Trunk Sewer, including 14,200 feet of 60-inch concrete pipe lined with 54-inch FRP pipe, 28 manholes, and four structures. (PST) on December 8, 2026. Bidders must obtain the Bid Documents through QuestCDN using project number 10394610 and watch a mandatory prebid walkthrough video. The project is subject to prevailing wage laws. Work must be completed within 450 working days after the Notice to Proceed.
On PublicBidSearch: the newspaper notice and the agency contact (name, email and phone) for this bid.
Contact
Agency contact for this bidName, email and phone — included with ProProOverview
- Due
- Dec 8, 2026
- Time stated in bid documents
- Dec 8, 2026, 2:00 PM Pacific Time
- Submission
- electronic portal
- Required submission items
- 1 items · full checklist with Pro
Scope of work
- Repair 28 manholes and 4 structures with protective coating/liner
- Complete all appurtenant work
Steps to Bid
- 1
Obtain the Bid Documents from QuestCDN using project number 10394610.
- 2
Watch the mandatory prebid jobsite walkthrough video on Official linkPro, available by October 14, 2026. was Oct 14, 2026
This date has passed — confirm eligibility with the agency before bidding.
What you'll need
Contract duration
450 working days from the Notice to Proceed
Submission
Electronic portal
NAICS
237130, 237199
Pursuit snapshot
Pro- Go / no-go verdict on every requirement
- 2 watch-outs that disqualify bidders
- The 1-item required-submittals checklist
Cancel anytime · no card to browse
Project details
2 is soliciting electronic bids for the rehabilitation of the Joint Outfall F Unit 3A Trunk Sewer, located in the cities of Bellflower and Cerritos, California. The work includes rehabilitating approximately 14,200 feet of existing 60-inch diameter corroded concrete pipe with 54-inch nominal diameter fiberglass reinforced plastic liner pipe, approximately 28 manholes and four (4) structures with a protective coating/liner, and all appurtenant work. (PST) on December 8, 2026. The official time is the [link available with Pro] bid clock. Only bidders who have properly downloaded the Bid Documents from QuestCDN will appear on the planholder list and may submit a bid. A mandatory prebid jobsite walkthrough video must be watched by all prime contractors before bidding. The video URL will be posted on the project’s webpage on [link available with Pro] by October 14, 2026. The electronic bid opening will occur on December 8, 2026, at 2:00 p.m. (PST).
Key dates
- Questions due
- Dec 1, 2026, 5:00 PM Pacific Time
- Bids due
- Dec 8, 2026
- Expected award
- Jan 13, 2027, 1:30 PM Pacific Time
More from this agency
- Joint Outfall A Unit 3C Trunk Sewer Protection Between Manholes A38 and A39 — closes Dec 1, 2026
Similar open bids
- IIGC Downtown Water and Sewer Improvements Phase II — City of Fresno
- North Orinda Sewer Renovations, Phase 9 — Central Contra Costa Sanitary District
- City of Corona Utilities Department Plumbing Services — City of Corona
- HD-S3262 On-Call Services for Underground Wet Utilities — Port of Long Beach
- RFQP On-Call Fuel Station Testing, Maintenance and Repairs — City of Bakersfield
Closing this week nearby
- Arbitrage Rebate Calculation and Analysis Services — closes Nov 23, 2026
- Tactical Combat Casualty Care (TCCC) Advanced Medical Training with Live Patient Models — closes Nov 23, 2026
- Wave Waterpark Restroom Remodel Project — closes Nov 23, 2026
- Esplanade Building 4 and Kalmus Building A Interior Improvements — closes Nov 23, 2026
- Inspector of Record for Playground Replacement at Montebello Gardens Elementary — closes Nov 23, 2026